Roots Update - 3/25/26
Lift Installation
The lift is now fully installed. There are still a few trim details and final adjustments to complete before it’s ready for public use, but its completion is imminent. Flooring installation in the upstairs and downstairs elevator hallways is expected to begin in the coming weeks.
Nursery Addition
Significant progress continues in the new nursery space. The ceiling grid is installed, and light fixtures are currently being set. The exterior HVAC unit is being placed, with ceiling registers scheduled for installation next week.
In the next couple of weeks, we plan to pour the sidewalk along the back of the building addition. Following Easter, we’ll begin demolition to connect the existing nursery to the new addition.
The lift is now fully installed. There are still a few trim details and final adjustments to complete before it’s ready for public use, but its completion is imminent. Flooring installation in the upstairs and downstairs elevator hallways is expected to begin in the coming weeks.
Nursery Addition
Significant progress continues in the new nursery space. The ceiling grid is installed, and light fixtures are currently being set. The exterior HVAC unit is being placed, with ceiling registers scheduled for installation next week.
In the next couple of weeks, we plan to pour the sidewalk along the back of the building addition. Following Easter, we’ll begin demolition to connect the existing nursery to the new addition.
Learn more about the Roots project and how you can give here.