Current Announcements

Stay in the know of the latest information and events.
Roots Update - 3/25/26
March 25th, 2026
Lift InstallationThe lift is now fully installed. There are still a few trim details and final adjustments to complete before it’s ready for public use, but its completion is imminent. Flooring installation in the upstairs and downstairs elevator hallways is expected to begin in the coming weeks.Nursery AdditionSignificant progress continues in the new nursery space. The ceiling grid is installed,...
Roots Update - 1/23/26
January 23rd, 2026
The elevator is making progress, with the goal to be operational Q1 2026. More equipment has been installed and the lift has undergone test operation, but work remains on the shaftway before it can be operational.The children's addition is dried in and its hvac unit is installed. The framers will be finishing up next week.New playground equipment is complete thanks to a great assembly crew.New roo...
Roots Update - 11/15/25
November 15th, 2025
The concrete slab for the children's classroom extension has been poured. Steel has been delivered and a crew will be on site the week of November 17 to start putting up the steel frame.Our contractor has completed the demotion and build back for the lift area and is making plans to proceed with construction in the upstairs area in preparation of installing the mast.Please continue to exercise cau...
Roots Update - 9/12/25
September 12th, 2025
The awning on the west side of the north building will be removed this week so that dirt work can be completed on the children's addition. Preparations for the concrete slab to be poured are expected by the end of next week. Demolition work has begun in the south building for the new lift's future location, and concrete work for lift is in progress (photo below). Straw and seed have been spread on...
Roots Update - 8/26/25
August 26th, 2025
Dirt work for the nursery addition has begun. Once complete, a concrete slab will be poured for the nursery addition as part of Phase 1 (currently expected to take place early September). Please exercise caution when walking near areas of active construction. Learn more about the Roots project and how you can give here.......

Get The App

Stay connected and get the latest content.

Download Now